College Strip Out, London

Overview

Location:

London

Type of Contractors:

Main

Timeline:

3 weeks

Summary:

strip-out-contractors39.jpg

Project Overview

We carried out a phased strip-out at a London school as part of a larger project to modernise teaching spaces.
We removed old layouts and finishes, making sure staff and students were not disrupted. We planned and coordinated closely because parts of the building stayed in use during the work.

Scope of Works

Our strip-out works included:
  • Removal of internal partitions and classroom reconfigurations
  • Strip out of suspended ceilings and floor finishes
  • Disconnection and removal of redundant mechanical and electrical services
  • Removal of fixed joinery, storage units, and fixtures
  • Careful protection of retained areas and structural elements
  • Waste segregation and responsible disposal
We followed all agreed risk assessments and safeguarding rules throughout the work.

Key Project Considerations

Working in a school meant we had to pay extra attention to safety, access, and communication.
For this project, we carefully managed:
  • Phasing works around school schedules
  • Strict segregation between working areas and operational spaces
  • Dust, noise, and vibration control measures
  • Controlled access routes and secure site boundaries
  • Close coordination with the school’s facilities management team
We put safety and safeguarding first at every stage.

Our Approach

Before starting, we reviewed the site to check access, service locations, and any constraints.
The project was delivered through:
  • Clear sequencing aligned with the refurbishment schedule
  • Experienced site supervision
  • Ongoing communication with school representatives
  • Continuous monitoring of safety and compliance measures
We kept the work safe and efficient by planning carefully and keeping tight control on site.

Outcome

We finished the project on schedule and handed back teaching areas clear, safe, and ready for the next stage.
Careful management of the strip out kept disruption low and set up the next stage of improvements.