Offices are the most common type of strip out, and the scope follows a familiar pattern. Soft strip means the non structural fit out: ceilings, partitions, floor finishes, fixtures and loose fittings. Hard strip goes further and removes the mechanical and electrical services, raised floors and non structural walls. Strip to shell takes everything back to the structure. Which one you need depends on what comes next, and it should be stated in writing before anyone prices the job.
Here is what each part of an office typically involves, and the thing that most often catches people out.
| Element | What is involved | What catches people out |
|---|---|---|
| Furniture and contents | Desks, chairs, storage, whiteboards, kitchen appliances, signage | Clearing contents is often assumed to be part of the strip out and frequently is not. Settle who removes what, and when, before the team mobilises. |
| Partitions | Stud walls, glazed screens, demountable systems, doors and frames | Stud partitions hide cabling and pipework. In older buildings some partition boards contain asbestos. Glazed screens need careful handling and often have resale value. |
| Ceilings | Tiles, grid, plasterboard sections, bulkheads, access panels | Everything above the ceiling is exposed when it comes down. Fire stopping, insulation and old cabling all become visible and become your problem. |
| Lighting and power | Light fittings, containment, small power, distribution boards | Circuits must be isolated and proven dead before removal. Some circuits feed other floors or tenants and have to stay live. |
| Heating, cooling and ventilation | Ductwork, fan coil units, split and VRF systems, pipework, grilles | Refrigerant must be recovered by a qualified engineer before units come out. Shared risers and chilled water circuits need careful isolation. |
| Data and comms | Cabling, cabinets, patch panels, wireless points, comms rooms | Redundant cabling left by previous occupiers is common. Live cabling serving neighbours must be identified and protected. |
| Floors | Carpet tiles, vinyl, raised access panels, pedestals, screed | Adhesive and old floor tiles can contain asbestos in older buildings. Raised floor panels are heavy and generate a lot of waste volume. |
| Kitchens and WCs | Units, appliances, sanitaryware, plumbing and waste connections | Water and drainage must be isolated and capped properly, not just cut. Poorly capped pipework causes leaks months later. |
| Fire and life safety | Detector heads, sprinkler heads, alarm sounders, emergency lighting | These systems stay live in the rest of the building. Changes need coordinating with building management and may need recertifying afterwards. |
After many office projects, the same items come up again and again as the ones clients did not expect. None of them are unusual. They just are not visible until work starts, which is why they are worth knowing about now.
Offices that have been occupied for years collect cabling from every previous fit out. Data, phone, security and AV cables get left in ceiling and floor voids when systems are replaced. Some of it is dead. Some of it is not, and no one has a drawing.
Plan for it: ask your IT or facilities team for comms drawings and have live circuits identified before work startsThese often contain UPS batteries, dedicated cooling and sometimes gas suppression systems. Batteries are hazardous waste and suppression cylinders need specialist decommissioning. A comms room is not a standard soft strip.
Plan for it: raise it at the survey stage so it is priced as a specialist itemSplit and VRF systems contain refrigerant gas that cannot simply be vented when the unit is removed. Recovery has to be carried out by an F Gas certified engineer, and the work should be recorded.
Plan for it: confirm the contractor has certified engineers or a named specialist, and ask for the recovery recordFluorescent tubes contain mercury and are classed as hazardous waste. LED fittings and control gear are electrical waste with their own recycling route. Neither belongs in a general skip.
Plan for it: check that lamps and fittings are segregated and that the paperwork covers themIn older buildings, black bitumen adhesive, thermoplastic floor tiles, textured coatings, insulation boards and ceiling tiles can all contain asbestos. A building does not have to look old to have it. Refurbishment history matters as much as build date.
Plan for it: commission the refurbishment and demolition survey first, before anything else is bookedFloor safes, archive storage, plant and heavy equipment often get forgotten until the team finds them. They need specialist lifting and sometimes structural checks before they can move.
Plan for it: walk the space with your contractor and point them outOld files, hard drives and laptops left in cupboards create a data protection problem the moment a contractor starts clearing the space. IT equipment also has to go through an electrical waste route.
Plan for it: clear and securely dispose of documents and devices yourself before the strip out startsEvery cable, pipe and duct that passes through a fire rated wall or floor has fire stopping around it. Removing services disturbs it. It has to be reinstated properly, and in some buildings it needs inspection and sign off afterwards.
Plan for it: make sure the quote includes reinstating fire stopping, not just removing servicesMost London offices sit inside a building run by a managing agent or landlord, with other tenants above, below or alongside you. That adds a layer of rules that do not apply in a standalone unit. These are the ones to find out about early, because several of them sit on the critical path.
Not every office strip out is the same job. The reason for the strip out shapes what matters most.
| Type of project | What it usually involves | What to focus on |
|---|---|---|
| Relocation or downsizing | Clearing a floor or suite you are leaving, often to a fixed move date | Contents clearance, IT decommissioning and working back from your lease or move date. |
| Ahead of a new fit out | Stripping the existing fit out so a new one can start, often by a separate contractor | A clean handover to the fit out team, with clear records of what services remain live. |
| Lease end reinstatement | Removing your fit out and returning the space to the condition your lease requires | The exact end condition in your lease and licence. See our guides to lease surrender strip outs and to CAT A and CAT B. |
| Landlord refurbishment | Stripping a vacant floor or whole building back to shell ahead of redevelopment | Scale, programme, asbestos and phasing by floor. |
| Partial strip, occupied floor | Stripping part of an office while the rest continues to operate | Dust, noise and access control. Often needs out of hours working. |
Most of the work that makes an office strip out go well happens before anyone picks up a tool. This is what to have in place.
A refurbishment and demolition survey is a legal requirement before strip out where asbestos may be present. Everything else is programmed around the result.
Furniture, files, personal items and equipment. Agree it in writing so nothing is assumed to be someone else's job.
Back up and wipe devices, disconnect and remove equipment, and tell your telecoms and internet providers about any line changes. Make sure nothing serving other tenants is touched.
As built drawings, riser layouts, comms drawings and any previous survey reports. The better the information, the fewer surprises once the ceiling is down.
Get contractor approval, method statement sign off and fire system isolation agreed. Ask whether your insurer needs to be told about works affecting alarms or sprinklers.
Lift bookings, loading bay slots, working hours, security passes and where skips or waste vehicles can go.
Item by item, not just back to shell or back to CAT A. State what stays, what goes, what standard of clean is expected and whether making good is included.
Take dated photographs of retained finishes, common parts and anything that could later be disputed. Take meter readings on the day work starts.
A tidy space is not the only deliverable. The paperwork is what protects you if anything is queried later, whether by a landlord, a surveyor or a regulator. At handover you should expect:
An office strip out is a well understood job, and most of the risk sits in the details people do not think to ask about. Contents, cabling, refrigerant, lamps, asbestos and the building's own rules. Get those settled before work starts and the strip out itself is the straightforward part.